This AD requires a detailed inspection of the FiP gasket at the engine fuel shutoff valve access panel for correct sealant installation, or a detailed inspection at the engine fuel shutoff valve access panel for any damage on the preformed seal, depending on configuration; a fluid leak test of the engine fuel shutoff valve access panel for any leak; and applicable on-condition actions.
Certain The Boeing Company Model 737-8, 737-9, and 737-8200 airplanes. Serial numbers and exceptions
Does it apply to your aircraft?
Enter an N-number to see every AD that names its model. Serial numbers and installed parts still decide.
This AD applies to The Boeing Company Model 737-8, 737-9, and 737-8200 airplanes, certificated in any category, as identified in Boeing Alert Requirements Bulletin 737-57A1358 RB, dated November 17, 2025.
The FAA is adopting a new airworthiness directive (AD) for certain The Boeing Company Model 737-8, 737-9, and 737-8200 airplanes. This AD was prompted by a leak through the form-in-place (FiP) gasket found during a leak check. This AD requires a detailed inspection of the FiP gasket at the engine fuel shutoff valve access panel for correct sealant installation, or a detailed inspection at the engine fuel shutoff valve access panel for any damage on the preformed seal, depending on configuration; a fluid leak test of the engine fuel shutoff valve access panel for any leak; and applicable on-condition actions. The FAA is issuing this AD to address the unsafe condition on these products.
Except as specified by paragraph (h) of this AD: At the applicable times specified in the “Compliance” paragraph of Boeing Alert Requirements Bulletin 737-57A1358 RB, dated November 17, 2025, do all applicable actions identified in, and in accordance with, the Accomplishment Instructions of Boeing Alert Requirements Bulletin 737-57A1358 RB, dated November 17, 2025.
Note 1 to paragraph (g): Guidance for accomplishing the actions required by this AD can be found in Boeing Alert Service Bulletin 737-57A1358, dated November 17, 2025, which is referred to in Boeing Alert Requirements Bulletin 737-57A1358 RB, dated November 17, 2025.
(1) Where the Compliance Time columns of the tables in the “Compliance” paragraph of Boeing Alert Requirements Bulletin 737-57A1358 RB, dated November 17, 2025, refer to the original issue date of Requirements Bulletin 737-57A1358 RB, this AD requires using the effective date of this AD.
(2) Where Boeing Alert Requirements Bulletin 737-57A1358 RB, dated November 17, 2025, specifies contacting Boeing for repair instructions: This AD requires doing the repair using a method approved in accordance with the procedures specified in paragraph (i) of this AD.
(3) Where Table 1 and Table 2 in Boeing Alert Requirements Bulletin 737-57A1358 RB, dated November 17, 2025, specifies “Do a fluid leak test of the engine fuel shutoff valve access panel for any leak. If any leak is found, do all applicable on-condition corrective action(s) and repeat the leak test until no leak is found”, this AD requires replacing that text with “Do a fluid leak test of the engine fuel shutoff valve access panel for any leak. If any leak is found, replace the FiP gasket and repeat the leak test until no leak is found”.
(4) Where Table 3 and Table 4 in Boeing Alert Requirements Bulletin 737-57A1358 RB, dated November 17, 2025, specifies “Do a fluid leak test of the engine fuel shutoff valve access panel for any leak. If any leak is found, do all applicable on-condition corrective action(s) and repeat the leak test until no leak is found”, this AD requires replacing that text with “Do a fluid leak test of the engine fuel shutoff valve access panel for any leak. If any leak is found, replace the existing sealant installation with a removable fay seal and repeat the leak test until no leak is found”.
(5) Where step 4.b. of Appendix A in Boeing Alert Requirements Bulletin 737-57A1358 RB, dated November 17, 2025, specifies “If any water leaks from the engine fuel shutoff valve access panel in less than two minutes, the fluid leak test has failed”, this AD requires replacing that text with “If any water leaks from the engine fuel shutoff valve access panel in less than two minutes, the fluid leak test has failed. Replace the FiP gasket in accordance with Figure 3 (Group 1) and removable fay seal in accordance with Figure 7 (Group 2), and repeat the leak test until no leak is found”.
(6) Where step 4.b. of Appendix B in Boeing Alert Requirements Bulletin 737-57A1358 RB, dated November 17, 2025, specifies “If any water leaks from the engine fuel shutoff valve access panel in less than two minutes, the fluid leak test has failed”, this AD requires replacing that text with “If any water leaks from the engine fuel shutoff valve access panel in less than two minutes, the fluid leak test has failed. Replace the FiP gasket in accordance with Figure 4 (Group 1) and removable fay seal in accordance with Figure 8 (Group 2), and repeat the leak test until no leak is found”.